Waste Management for the Britannia and
Lemieux Island WPPs Project


The process waste generated at the Britannia and Lemieux Island Water Purification Plants (WPPs) originates from both the settling and filter backwashing processes. Since the plants were built, these process wastes from the plants, comprised of settled and filtered particulate materials, have been discharged back to the Ottawa River.

Following provincial orders to discontinue this practice, the City of Ottawa completed a study in October 2002 that followed the Municipal Class Environmental Assessment (Class EA) process for a Schedule B project, to select a management practice to divert these materials from the river.

The selected alternative consisted of discharging the process sludges to the City's sanitary collection system for treatment at ROPEC. The project is currently in the design phase and construction is scheduled to begin in this spring.

For more information and/or to submit comments, please contact:

M. Ted Woytowich, P.Eng.
Senior Project Manager
100 Constellation Cres.
6th floor
Nepean ON K2G 6J8

Phone : 613-580-2424 Ext. 22721
Fax : 613-560-6064

E-mail : Theodore.Woytowich@ottawa.ca

Norm Newman, P.Eng
Senior Project Engineer
CH2M HILL
1101 Prince of Wales Drive, Suite 330
Ottawa ON K2C 3W7

Phone : 613-723-8700, Ext. 224
Fax : 613-723-7489

E-mail : norm.newman@ch2m.com